Saturday, January 25, 2020
Causes of Construction Delays
Causes of Construction Delays    This chapter gives an idea of what construction delays are, how are they defined and what are their types and comparison of them. Delays can be seen differently from different point of views. Causes of delays and categorization of them in various international contexts are also discussed.  2.2 DEFINING CONSTRUCTION DELAY  A lot of work has been done before on construction delays and every author came up with his/her own definition.  Assaf and Hejji defined delay as Time overrun either beyond completion date specified in a contract, or beyond the date that the parties agreed upon for delivery of a project slipping over its planned schedule. (Assaf, Hejji, 2006)  Stumpf defined delay as Act or event that extends the time required to perform a task under a contract. It usually shows up as additional days of work or as delayed start of an activity. (Stumpf, 2000). And many similar definitions were given.  Therefore construction delays can be considered as time lag in completion of activities from a fixed time as per contract or they can be defined as late completion or late start of activities to the planned schedule or contract schedule. When project delay occurs it means project cannot be completed within stated time, which means there will be extensions of time required which will further result in fine, increased cost due to inflation, termination of contract, court cases etc. or combinations of above stated factors.  Delay can be seen as risk for the project and could be handled at inception stage or at least one can try to mitigate or minimize it. Risk is an integral part of a construction project; it is well known that no project is risk free. If risk is analysed at inception or planning stage it could be managed, minimized, shared, mitigated or accepted to give some good results. Delay can be considered similar to risk or a type of risk; as no construction project is free from delays, delay is also integrated part of construction projects. It depends on size of project as well. Therefore it is expected to analyse and manage delay in same fashion as risk.  Delays are often result of a mismanaged event which must have been managed in a systematic process so as to analyse the effect of that event on the project and how to minimize chances of further delay. (Keane, Caletka, 2008).  2.3 CATEGORIZATION AND TYPES OF CONSTRUCTION DELAYS  Before getting on types of various construction delays there is a major categorisation which is required to be understood. Construction delays can be delayed in some major groups as listed below.  El-Saadi (1998) categorized delay in four major groups.  Critical or Non critical  Excusable or Non Excusable  Compensable or Non Compensable  Concurrent or Non concurrent  Alkaas S., Mazerolle M. and Harris F. (1996) and Ahmed S.M. et al gave following categorizations:  Excusable Delays  Excusable compensable delays  Excusable noncompensable delays  Nonexcusable delays  Concurrent delays  Fig. 2.1 Classification of delay based on their various attributes. Nuhu Braimah (2008)  To achieve objectives of this dissertation and to consider delay as risk it is necessary to know about these types of delays and as per categorization in what category they lie. This basic knowledge helps in moving forward and determining strategies to mitigate these risks. Now in this part we will discuss these types of delay in detail:  2.3.1 CRITICAL AND NON CRITICAL  In simple words Critical delays are those which cause delay to entire project completion date while Non critical delays not necessarily affect the project completion date but affects progress. In all the projects delays are considered at the project completion date. Delays can be combination of small and big delays that occurred during the whole project. Therefore critical delays are taken more into consideration then noncritical delays.  2.3.2 EXCUSABLE DELAYS  Excusable Delays occurs due to events which are outside the control of contractor like heavy rains, storms, strikes, fire, client suggested changes, differing site conditions, change of government policy or their intervention, stakeholder intervention etc.  Alkass S. et al (1996) says that when there are excusable delays, contractor is entitled to time extension in case date of completion is extended. Such delays can also affect non critical activities which must be considered with more detailed analysis or adjustment of float time.  Excusable delays can be further classified in compensable and noncompensable delays.  2.3.2.1 EXCUSABLE COMPENSABLE DELAYS  As name suggests excusable compensable delays are those in which contractor is entitled for extra payment (compensation) i.e. monetary compensation and time extension as well. But decision that a delay is compensable or noncompensable is taken as per contract between client and contractor. Natural disasters or some reasons which are out of control are not considered. Example of such delay could be that client doesnà ¢Ã¢â ¬Ã¢â ¢t allow access to site even after notice to proceed is given; other such delays which are due to client are compensable.  2.3.2.2 EXCUSABLE NONCOMPENSABLE DELAYS  Such delays are such where both contractor and client are not responsible for delay. Under such circumstances only time extensions are granted and no monetary compensation is provided. Such delays include act of God.  2.3.3 NON EXCUSABLE DELAYS  As name suggests these delays are such that they donà ¢Ã¢â ¬Ã¢â ¢t have any excuse or no excuse can be given for them. They arise due to carelessness or actions and inactions of contractors and subcontractors. For such delays no time extensions and monetary compensation is given to contractor if it has affected whole duration of project. In such cases client is liable to get liquidated damages. Example of such delay could be constructing something wrong which is not given in drawings, not completing work on time, improper resource allocation etc.  2.3.4 CONCURRENT DELAYS  This is the most complex categorization of delay as it consists of two or more kind of delays regardless of their type which occurs at same time or overlaps some duration together. It is necessary to find out what type has caused overall delay in project completion. Therefore different factors like time of occurrence of delay, duration of delay, impact of them, float ownership etc. have to be considered carefully.  Alkass et al (1996) said that; Concurrent delays which contains two or more excusable delays results in time extension. When compensable and nonexcusable delays are concurrent a time extension can be given or delay can be distributed between client and contractor.  2.4 CAUSES OF CONSTRUCTION DELAYS  In section 2.3, categorisation of delays was discussed. Now in this section will deal with causes of delays. Lot of work has been done on understanding causes of delays. The two major categorization of delay causes one is Internal Cause another is External Cause.  Internal cause includes delays caused by parties involved in construction project like Client, Contractor, Designer, Consultant these are four major parties then Subcontractors, material suppliers etc. comes. From external factors it includes act of God, strikes, stakeholderà ¢Ã¢â ¬Ã¢â ¢s dissatisfaction etc.  Assaf and Hejji (2006) reflected various causes of delays which occur in large construction projects. They had a field survey of 23 contractors, 19 consultants, and 15 owners and found out and reflected on 73 causes of delays under eight different groups. All those 73 factors are given in table below.  NO.  CAUSES OF DELAY  GROUP  1  Original contract duration is too short.  Project  2  Legal disputes b/w various parties.  Project  3  Inadequate definition of substantial completion.  Project  4  In effective delay penalties.  Project  5  Type of construction contracts.  Project  6  Type of project bidding and award  Project  7  Delay in progress payment by owner.  Owner  8  Delay to furnish and deliver the site to contractor by the owner.  Owner  9  Change orders by owner during construction.  Owner  10  Late in revising and approving design documents by owner  Owner  11  Delay in approving shop drawings and sample materials  Owner  12  Poor communication and co-ordination by owner and other parties  Owner  13  Slowness is decision making process by owner  Owner  14  Conflicts between joint ownership of the project  Owner  15  Unavailability of incentives for contractors for finishing ahead of schedule  Owner  16  Suspension of work by owner  Owner  17  Difficulties in financing project by contractor.  Contractor  18  Conflicts in subcontractors schedule in execution of project  Contractor  19  Rework due to errors during construction.  Contractor  20  Poor site management and supervision by contractor  Contractor  21  Poor communication and co-ordination by contractor with other parties  Contractor  22  Ineffective planning and scheduling of project by contractor  Contractor  23  Improper construction methods implemented by contractor.  Contractor  24  Delays in subcontractors work  Contractor  25  Conflicts between contractor and other parties  Contractor  26  Inadequate contractors work.  Contractor  27  Frequent change of subcontractors due to their insufficient work.  Contractor  28  Poor qualification of the contractors technical staff  Contractor  29  Delay in site mobilization.  Contractor  30  Delay in performing inspection and testing by consultant  Consultant  31  Delay in approving major changes in the scope of work by consultant  Consultant  32  Inflexibility (rigidity) of consultant  Consultant  33  Poor communication and co-ordination by consultant with other parties  Consultant  34  Late in reviewing and approving design documents by consultants  Consultant  35  Conflicts between consultant and design engineer.  Consultant  36  Inadequate experience of dsigner.  Consultant  37  Mistakes and discrepancies in design documents  Design  38  Delays in producing design documents  Design  39  Unclear and inadequate details in drawings  Design  40  Complexity of project design  Design  41  Insufficient data collection and survey before design  Design  42  Misunderstanding of ownerà ¢Ã¢â ¬Ã¢â ¢s requirement by design engineer.  Design  43  Inadequate design team experience  Design  44  Un-use of advanced engineering design software.  Design  45  Shortage of construction materials in market  Material  46  Changes in material types and specification during construction  Material  47  Detail in material delivery.  Material  48  Damage of sorted material while they are needed urgently.  Material  49  Delay in manufacturing special building material  Material  50  Late procurement of materials  Material  51  Late in selection of finishing materials due to availability of many types in market  Material  52  Equipment breakdowns  Equipment  53  Shortage of equipment  Equipment  54  Low level of equipment-operatorà ¢Ã¢â ¬Ã¢â ¢s skill  Equipment  55  Low productivity and efficiency of equipment  Equipment  56  Lack of high technology mechanical equipment  Equipment  57  Shortage of labours  Labours  58  Unqualified workforce  Labours  59  Nationality of labours  Labours  60  Low productivity level of labours  Labours  61  Personal conflict among labours  Labours  62  Effects of subsurface conditions  External  63  Delay in obtaining permit from government  External  64  Hot weather effects on construction activities  External  65  Rain effect on construction activities  External  66  Unavailability of utilities in site  External  67  Effect of social and cultural factors  External  68  Traffic control and restriction at job site  External  69  Accident during construction  External  70  Differing site conditions  External  71  Changes in government regulations and laws  External  72  Delay in providing services from utilities  External  73  Delay in performing final inspection and certification by a third party  External  Table 2.1 Causes of delays as per group Assaf and Hejji (2006)  Their work gave a broad view over construction delays and their causes. Though their classification is quite broad, but it gives a more insight to various causes.  Odeh AM and Battaineh HT (2002) presented following 8 major groups of construction delay.  Client related factors which include finance, payment of billed work, interference in work, slow decision making etc.  Contractor related factors include site management, improper planning, insufficient experience, improper construction methods, insufficient and unskilled work force etc.  Consultant related factors include contract management, improper drawings, approval of drawings, tests at site etc.  Material related factors include availability, quality and shortage.  Labor and equipment factors include supply, productivity, equipment availability, failure etc.  Contract factors include changed orders and mistakes and disagreements in document.  Contractual relationship factors includes, disputes, negotiation, improper management of information system, improper work breakdown structure and task responsibility matrix.  External factors like act of god, strikes, accidents etc.  Most of the work done in field of causes of delays reflects similar causes of delays and 8 major groups. They all gave recommendations related to these factors but very few scholars suggested to forecast delay in planning stage. Khalil and Ghaftly (1999) said delay is important issue. In order to manage it more properly and to mitigate them deep investigation to this area is needed. Having idea of frequency, extent and responsibility of delay can provide insights of early planning to control these factors and improve project performance.  2.5 PERSPECTIVE FROM DIFFERENT COUNTRIES  Work from Chan and Kumaraswamy (2002) from Hong Kong industry gives four major causes of delay in Hong Kong industry which are as follows:  Project scope  Project complexity  Project Environment  Management related attributes  The above four factors were studied with their constituent casual factors to gain more insight and understanding of their significance. They were summarized in following figure:  Figure 2.3 Summary of principal factors affecting construction durations of projects  He gave another table comparing factors causing delay in construction projects in various economies. It gives an overview of common factors in these economies. It gives a clear understanding of various countries at once.  Factors Causing Delay  Countries where survey was conducted  US  UK  DEVELOPING COUNTRIES  TURKEY  NIGERIA  SAUDI ARABIA  HONG KONG  INDONESIA  Inclement weather  *  *  *  *  *  Labour shortage/ Low labour productivity  *  *  *  Poor subcontractorà ¢Ã¢â ¬Ã¢â ¢s performance  *  *  *  *  Variations (design change/ extra work)  *  *  *  *  *  Unforeseen ground conditions  *  *  Materials shortage/ late material delivery  *  *  *  Inadequate construction planning  *  *  *  Financial difficulties  *  *  *  Delays in design work/Lack of design information  *  Poor site management  *  *  *  *  Impractical design  *  Poor communication  *  *  Inappropriate type of contract used  *  Lack of designerà ¢Ã¢â ¬Ã¢â ¢s experience  *  Inaccurate estimating  *  *  *  Table 2.2 Source: Chan and Kumarswamy (2001)  Ogunlana and Promkuntong studied and compared construction industry of Thailand and other economies. Study involved delays experienced in the High Rise Building construction projects in Bangkok, Thailand. According to them Resource supply problem were most acute problems of the construction industry in boom years. Project suffered delays due to inadequate supply of cement, technical personnel were overstretched, and demands from owners to do frequent changes etc. are the major causes for delay in developing economy.  Sabasivan and Soon (2007) conducted study of causes of delay in Malaysian construction industry. They conducted a survey and 150 participants were involved. They came up with 10 most important causes of delay which are as follows:  Improper planning of contractor.  Poor site management from contractor  Inadequate experience of contractor  Improper payments and finance from client  Subcontractors problem  Material shortage  Labour supply  Failure and availability of equipment  Improper management information system  Mistakes during construction stage.  COUNTRY  RESEARCHERS  MAJOR CAUSES OF DELAYS  Saudi Arabia  Assaf et al  Slow preparation and approval of shop drawings  Delays in payments to contractors  Changes in design/design error  Shortages of labour supply  Poor workmanship  Lebanon  Mezher et al  Owner had more concerns with regard to financial issues  Contractors regarded contractual relationships the most important  Consultants considered project management issues to be the most important causes of delay  Saudi Arabia  Al-khal and Al-Ghafly  Cash flow problems/financial difficulties  Difficulties in obtaining permits  à ¢Ã¢â ¬Ã
âlowest bid win firstà ¢Ã¢â ¬? system  Jordan  Al-Moumani  Poor design  Changes in orders/design  Weather  Unforeseen site condition  Late deliveries  Kuwait  Koushki et al  Changing orders  Owners financial constraints  Ownerà ¢Ã¢â ¬Ã¢â ¢s lack of experience in the construction business  UAE  Faridi and El-Sayegh  Slow preparation and approval of drawings  Inadequate early planning of project  Slow decision making of owners  Shortage of manpower  Poor site management and supervision  Low productivity of manpower  Saudi Arabia  Assaf and Al-Hejji  Change in orders by the owner during construction  Delay in progress payment  Ineffective planning and scheduling  Shortage of labour  Difficulties in financing on the part of contractor.  Hong Kong  Chan and Kumaraswamy  Project scope  Project complexity  Project environment  Management related attributes  Florida  Ahmed and Azhar  Design related  Construction related  Financial/economical  Management/ Administrative  Code related  Acts of God  Table 2.3 Summary of previous studies of the causes of delay in construction project some data from above table is taken from Sweis et al (2008)  2.6 SUMMARY:  A total of 73 factors and 8 major groups of causes of construction delays were identified through intensive literature reviews in order to consider maximum factors. These factors will be helpful in data analysis so as to forecast delay at planning stage and treat it as risk so that risk management methodologies can be implemented to delay so as to mitigate and minimizing it.  These eight major categories can be brought down as shown in figure.  Fig 2.4 Classification of delay groups.  All major 8 groups can be brought down to 2 major groups which are Internal and external causes. Internal is further subdivided in owner, consultant, contractor and resources. Resources are further subdivided in Material, equipment and labour.  Overall if we need to classify groups for the causes of delay 5 major groups covers all 73 factors they are Owner, Contractor, Consultant, Resources and External.  These causes and classification will help us to rank and treat delay as a risk at planning stage so as remedial measures can be applied. Though in spite of all studies and delay causes know till now it is hard to forecast delay because its very unpredictable, we cant analyse frequency of delay due to some reason in a project. Sometimes external causes are so dominating that co-ordination of internal groups get disturbed and project faces delay.    
Friday, January 17, 2020
A Person Who Has Succeeded In Life Essay
It is lunch hour. A large restaurant located in the heart of Kuala Lumpur city is packed with regular customers. Waiters and waitresses are busy serving the customers. Outside the restaurant, the owner of the restaurant is seen arriving in a luxury car. After parking his car, he enters the restaurant and starts mingling with the customers. The humble man is none other than my beloved grandfather. My grandfather is a man of little education. He comes from a poor family. After attending primary school, he had to stop schooling due to poverty.  As the eldest son of the family, he helped his father at his stall selling barbecued meats. Life was indeed difficult for him then. He had to get up early in the morning before dawn and go to the market together with his father to buy fresh chickens and ducks. Then, they returned home to slaughter them, prepare the meats and barbecue them. My grandfather was extremely interested in culinary skills. As a teenager, he was a fast learner and was able to prepare the meats as well as his father before long. One morning, my grandfather woke up early in the morning as usual.  He assumed that everything would go on smoothly but little did he know that he had lost his father. When he went to wake his father up, there was no response from him. My grandfather panicked and called for an ambulance. When his father was sent to hospital, he was pronounced dead on arrival by a doctor. My grandfather was totally devastated by the sudden demise of his father. In the midst of his sadness, he knew he had to find strength to carry on. To earn a living, he had no alternative but to take over the stall that his father left behind.  Using the small savings that he inherited from his father, he continued with the business. He learnt about finance from his own experience and whatever he could recall when he was with his father. He led a frugal lifestyle and only spent money when it was necessary. He was so thrifty that when he got married a few years later, his guests were only treated to rice and barbecued meats. He was industrious and saved as much money as he could. He kept his savings in a bank. After a couple of years, his diligence and modesty finally paid off ââ¬â he had saved enough money to open a restaurant.  Thanks to his excellent management skills that he acquired earlier, his restaurant prospered and his business expanded. Apart from selling barbecued meats, he also sold other food such as chicken rice, economical meals, dim sum and a variety of noodles. Today, my grandfather is an extremely successful and well-established restaurateur. He often advises me to study hard and be a knowledgeable person in order to contribute to society in future. He also emphasises the virtues of diligence, frugality and honesty. I will not forget his advices for as long as I live because he is my role model.  A Person Who Has Succeeded In Life Essay  It is lunch hour. A large restaurant located in the heart of Kuala Lumpur city is packed with regular customers. Waiters and waitresses are busy serving the customers. Outside the restaurant, the owner of the restaurant is seen arriving in a luxury car. After parking his car, he enters the restaurant and starts mingling with the customers. The humble man is none other than my beloved grandfather. My grandfather is a man of little education. He comes from a poor family. After attending primary school, he had to stop schooling due to poverty.  As the eldest son of the family, he helped his father at his stall selling barbecued meats. Life was indeed difficult for him then. He had to get up early in the morning before dawn and go to the market together with his father to buy fresh chickens and ducks. Then, they returned home to slaughter them, prepare the meats and barbecue them. My grandfather was extremely interested in culinary skills. As a teenager, he was a fast learner and was able to prepare the meats as well as his father before long. One morning, my grandfather woke up early in the morning as usual.  He assumed that everything would go on smoothly but little did he know that he had lost his father. When he went to wake his father up, there was no response from him. My grandfather panicked and called for an ambulance. When his father was sent to hospital, he was pronounced dead on arrival by a doctor. My grandfather was totally devastated by the sudden demise of his father. In the midst of his sadness, he knew he had to find strength to carry on. To earn a living, he had no alternative but to take over the stall that his father left behind.  Using the small savings that he inherited from his father, he continued with the business. He learnt about finance from his own experience and whatever he could recall when he was with his father. He led a frugal lifestyle and only spent money when it was necessary. He was so thrifty that when he got married a few years later, his guests were only treated to rice and barbecued meats. He was industrious and saved as much money as he could. He kept his savings in a bank. After a couple of years, his diligence and modesty finally paid off ââ¬â he had saved enough money to open a restaurant.  Thanks to his excellent management skills that he acquired earlier, his restaurant prospered and his business expanded. Apart from selling barbecued meats, he also sold other food such as chicken rice, economical meals, dim sum and a variety of noodles. Today, my grandfather is an extremely successful and well-established restaurateur. He often advises me to study hard and be a knowledgeable person in order to contribute to society in future. He also emphasises the virtues of diligence, frugality and honesty. I will not forget his advices for as long as I live because he is my role model.    
Thursday, January 9, 2020
Othello and Frankenstein Essay - 1929 Words
  From Man to Monster When monsters are thought of a very distinct picture comes to mind. An ugly creature that is out for blood, born into a life where causing misery is his driving force. Do these features really define what a monster is; works of literature like Mary Shelleyââ¬â¢s Frankenstein and Shakespeareââ¬â¢s Othello tell quite a different story. Monsters are not born but made just as people are not born evil but can sometimes end up there. Othello and the Monster start of as good men looking to be part of society but were pushed out because of what others perceived them to be.  This caused them to mentally and physically isolate themselves from everyone allowing hatred to take over. Iago and Frankenstein also helped to instill thoughtsâ⬠¦show more contentâ⬠¦Since Othello is being manipulated he finds it hard to be around any one causing him to separate himself from his loved ones and colleagues. When asking to speak with Desdemona to question her on her infideli   ty he tells her, ââ¬Å"Get you to bed on thââ¬â¢ instant. I will be returned/ forth with. Dismiss your attendant there. Lookââ¬â¢t be/ done.â⬠ (Shakespeare IV, iii, 7-9). He is uncomfortable talking to her in the presence of Emilia, almost like an outsider being involved would confuse him further. His separation from all other characters other than Iago keeps him from knowing the truth. This causes his mind to run wild and come up with reasons that justify him in his monstrous actions that have become more frequent. However, in comparison the Monsters physical isolation causes him to mentally isolate himself. After being abandon by Frankenstein the Monster is forced to live on his own in the woods. Realizing that human kind will never truly accept him he asks Victor to create him a mate stating, ââ¬Å"I am alone and miserable man will not associate with meâ⬠ (Shelley, 118). When Victor ultimately denies the Monster of companionship he becomes enraged again continui   ng to lose his faith in mankind. The Monsters physical segregation fuels his mental isolation whole Othelloââ¬â¢s mental isolation fuels his physical segregation. Othello and the Monster are also mentally isolated in very different ways. Othelloââ¬â¢s mental isolation is driven by Iagoââ¬â¢s manipulation.Show MoreRelatedThe Evil Of The Monster By Mary Shelley s Frankenstein1048 Words à  |à  5 PagesShelleyââ¬â¢s Frankenstein, the monster commits a number of immoral acts out of rage. These actions are directly related to the monsters creation and upbringing. The burden of fault for the monsters actions rests on Victor Frankensteinââ¬â¢s shoulders alone.  The lack of attention Frankenstein contributed towards the monster, and his life teaching, is directly correlated with the actions the creature made throughout his existence. Although the creature physically caused the murders, Victor Frankenstein instigatedRead MoreEssay Prompts4057 Words à  |à  17 PagesAP ENGLISH LIT AND COMP  FREE RESPONSE QUESTIONS    2004  (Form A): Critic Roland Barthes has said, ââ¬Å"Literature is the question minus the answer.â⬠ Choose a novel or play and, considering Barthesââ¬â¢ Observation, write an essay in which you analyze a central question the work raises and the extent to which it offers any answers. Explain how the authorââ¬â¢s treatment of this question affects your understanding of the work as a whole. Avoid mere plot summary.    You may select a work from the list below or anotherRead MoreAmerican Literature11652 Words à  |à  47 Pagesattitudes emergence of ethnic writers and women writers    Style:  ï⠷ ï⠷ ï⠷ ï⠷ ï⠷ ï⠷ ï⠷    narratives: both fiction and nonfiction anti-heroes concern with connections between people emotion-provoking humorous irony storytelling emphasized autobiographical essays    Effect:  ï⠷    too soon to tell    Historical Context:  ï⠷ ï⠷    people beginning a new century and a new millennium media culture interprets values    Analyzing Poetry: Poetry Tips  Analyzing Poetry  What is poetry? How is it analyzed? What are    
Wednesday, January 1, 2020
Terrorism And The United States - 1981 Words
  Introduction  Today when we think of terrorism and terrorist as being something grown out of radical and fundamentalist Islamic Societies in the middle east. However, terrorism does not have to come from abroad. Terrorism can be homegrown in America and for the past 40 years that is what has been happening in cities all across the United States. Gang related terrorism is extremely high in inner cities all across the country and the Crips are the largest gang that operates in America. In 1970ââ¬â¢s California the Crips were created as a response to protect their neighborhoods but have grown to much more than that. Today there are over 33,000 members of this terror organization who use murder as one of their top fear tactics. Through theirâ⬠¦show more contentâ⬠¦Raymond Washington has been credited with creating the gang while still in High School at Freemont. It was originally created as a political organization which grew to provide protection from other gangs and profit from criminal ac   tivity. Washington imitated the Black Panther party when creating the organization of the Crips and after the help of a few other original members in recruiting young men they increase the gangââ¬â¢s involvement in violent criminal activity. Initially there was no formal leadership in the gang how ever leaders were recognized by other members due to their charismatic personalities and influence. These leaders would make it a priority to expand the reach of the gang and expand the influence and power that the Crips had. By 1978 they had already grown to 45 separate gangs showing how quickly their ideas and influence caught on it Los Angeles. The Crips first main illegal activity was the promoting and distribution of the drug PCP. This allowed for them to acquire a large cash flow while at the same time expanding their influence in areas that they had not been in before. With the sell of PCP, the gang would also include marijuana and other small street drugs into the forte of illic   it narcotic sales. They were seen as a large supplier of narcotics in Los Angeles at the time. The introduction of crack cocaine by the Crips in the 1980ââ¬â¢s made them one of the most successful organizations in the U.S. and created a need for them to    
Subscribe to:
Comments (Atom)
 
